Project : Scrivner Field Site Improvements

Nearly 6,000 sf of concrete sitework was installed beneath the existing bleachers and around the dugouts to address weather and accessibility issues. Two catch basins were also installed in the concrete to allow for proper storm water drainage into the campus storm drain system.

Construction was completed in August 2011. Total construction cost was $65,925.

Proposals for new drought-tolerant landscaping near the dugouts and behind the bleachers are currently under review.

Installation is scheduled for January 2012. Total project cost is estimated to be $23,000.